Permit Application Requirements & Guidelines
Links for the permit applications are often found at the bottom of relevant pages under Supporting Documents . Once you have read through all requirements, downloaded, and filled out all necessary documents, you can apply and upload them at Oregon ePermitting, or you can email them to the Building Department at bld@crookcountyor.gov. If you are applying online, please read these instructions for applying online.
If your subdivision requires fire sprinklers, those plans are required to be submitted concurrently with structural plans.
PLEASE NOTE: Parks & Recreation Fee
First time development of property (dwellings only) that falls in the Crook County Parks and Recreation District must pay a Parks & Rec fee prior to the issuance of a dwelling or manufactured home permit. To find out what this fee is, please contact the City of Prineville at: (541) 447-2367. Payments are taken at Prineville City Hall.
COMMON PERMITS
New Single Family Dwelling
Needed with Application:
- One set of large (24" x 36") building plans
- One set of truss plans (if trusses are being used; 8 1/2" x 11")
- One set of engineer calculations (8 1/2" x 11")
- One 8 1/2" x 11" copy of the site plan showing setbacks and distances between structures
Manufactured Home
Our manufactured home application asks for utilities going to the home. However, if applicable, additional permits may be created off this application for work that isn't covered under a manufactured home permit. Contact the office to determine all permits that will be created off this application.
Needed with Application:
- Home floor plan
- One 8 1/2" x 11" site plan showing setbacks and distances between structures
- If the home isn't new, a picture of the HUD sticker is required.
Accessory Building, Addition, Remodel
Needed with Application:
- One complete set of building plans (24"x36")
- One set of truss plans (if trusses are being used)
- One set of engineer calculations
- One 8 1/2" x 11" site plan showing setbacks and distances between structures.
SIMPLE PERMITS
Electrical
- Complete the second page of the application to determine if a plan review is required.
Mechanical
- Complete the second page of the application to determine if a plan review is required.
Plumbing
- Complete the second page of the application to determine if a plan review is required.
MISCELLANEOUS PERMITS
Equine/Agricultural Exempt
- Subject to zoning requirements. Contact the Planning Department for details.
Demo
- Asbestos survey may be required prior to demolition for certain structures.
Solar
- Over 25 KVA requires an electrical plan review. If you answer NO to any of the questions on the Solar Checklist , it will require a structural plan review.